Day 31 - A three-man crew installed the roof drip edge, roof edge surround and gutters today. They also installed edge framing for siding and started installing ceiling panels that will support the decorative ceiling panels to be installed tomorrow. The electrician was here during late afternoon and installed the two floodlights on the back of the sunroom roof. The electrician will return on Wednesday to complete the installation of ceiling lights, duplex outlets and switches.
There continues to be a delay in glass window fabrication, but the glass windows for the upper section of the west wall were delivered today, along with temporary vinyl windows for the large window panels.