Friday, September 9, 2022

Day 30 - Busy day here. A two-man crew fabricated flashing for the roof edges and a third man worked on the soffit for the corner of the family room roof. The county inspector arrived mid-morning and signed off on the structural, mechanical and electrical permits, meaning there are no further permitting issues to complete the project. The men applied adhesive to the floor joists and re-installed the floor boards, securing with screws. They also installed all of the drywall on the wall next to the family room and attic.


Consulting with company representative waiting for county inspector


County inspector approving all permits


Installing floorboards




Installing soffit and flashing



Drywall prep



Installing drywall



Completed drywall


Metal brake for forming flashing





End of day overview



But wait....there's more!

The natural gas fireplace insert that we ordered in March finally arrived today for installation in our family room. A two-man crew worked all day replacing the old unit with the new one. Here are some photos of the events:

Removing siding and cutting exterior chimney wall




Old unit to be pulled



Removing chimney surround



Chimney surround


Old unit removed




Moving in new unit




Air supply/exhaust pipe



New insert in position


Connected to gas and electric - ready to test


Replacing siding and support structure



Completed siding and vent



Completed installation




No comments:

Post a Comment

 Windows! We were surprised today with the delivery of the last four glass windows for the west wall. Unfortunately, three of the four windo...