Day 24 - The carpenters installed 2x4 framing in the sunroom ceiling to provide space for wiring the ceiling lights and fan. This will also be the mounting frame for the finished wood panelling that will cover the ceiling. The carpenters also built the steps with temporary lumber that will be replaced when more is available on site. They started the installation of Versatex white board on the side of the deck and modified the end of the bench with a decorative cut.
The electrician arrived in the afternoon and wired the outlets in the sunroom. He will return tomorrow morning to complete the rough-in electrical with the goal of having an inspection on Friday. The glass for the west wall is still on back order.
A contractor was here this morning to take measurements in the sunroom for the installation of the porcelain floor tiles that we have on order.