Day 32 - A two-man crew delivered additional ceiling mounting boards and stored them in the sunroom for installation tomorrow. They installed the remaining siding panels on the house, next to the north side of the sunroom. They spent the remainder of the day installing framing for the west wall windows, and installed the four lower temporary windows and two of the upper windows, leaving two more to complete tomorrow.
Tuesday, September 13, 2022
Subscribe to:
Post Comments (Atom)
Windows! We were surprised today with the delivery of the last four glass windows for the west wall. Unfortunately, three of the four windo...
-
Windows! We were surprised today with the delivery of the last four glass windows for the west wall. Unfortunately, three of the four windo...
-
The remaining tiles were installed today, and will be ready for grouting tomorrow. We look forward to being able to use the sunroom on Frida...
-
Day 26 - There were no installers yesterday, but the electrician worked today to finish the rough-in wiring in preparation for the inspectio...











No comments:
Post a Comment