Landscaping Day 5 - The 4-man crew arrived at 9:45 with a truckload of mulch and more plants. They completed the pathways and retaining walls, hauled topsoil, and distributed the trees and plants to their designated spots. Several of the trees and plants were in the ground before the end of work. A double crew is scheduled to complete all planting, top soil and mulch work tomorrow, and the drip irrigation system will be installed on Tuesday.
One of the sunroom contractors finished cutting the ceiling holes for the ceiling lights.The elecrician completed installing the remaining duplex outlets and the six LED ceiling lights. He has scheduled the final electrical inspection for next Tuesday. The tile contractor will install the Durock base for the floor tiles on Monday. Tile installation is pending scheduling.