Day 21 - The two-man window crew finished installing the two remaining windows on the south wall this morning. The roofers did not appear, and the expected delivery of the windows for the west wall has been delayed until Monday, so this was a short work day.
Friday, August 26, 2022
Subscribe to:
Post Comments (Atom)
Windows! We were surprised today with the delivery of the last four glass windows for the west wall. Unfortunately, three of the four windo...
-
Landscaping Day 5 - The 4-man crew arrived at 9:45 with a truckload of mulch and more plants. They completed the pathways and retaining wall...
-
Landscaping day 4 - A large pile of topsoil was deposited on the street in front of our house early this morning. A four-man crew arrived at...
-
Day 26 - There were no installers yesterday, but the electrician worked today to finish the rough-in wiring in preparation for the inspectio...