Day 20 - A contractor and I installed a temporary support to raise the lower guy cable 5" above the edge of the sunroof. A permanent solution will include the installation of an extension of the guy post. 

A two-man crew installed most of the window/door panels today, until they were interrupted by an unforecast rainstorm at 2:50pm. Another delivery of window panels is expected tomorrow to complete the glass installation.

Temporary elevated support for lower guy cable



Installing sliding doors


Window delivery


Installing glass panels and trim




Completed north wall




South wall - installation interrupted by rain



Remaining panels for south wall


End of day overview