Day 12 - A two-man crew installed the lattice support around the sunroom and started the supports for the deck lattice. The Trex deck boards were delivered today, along with all the boards and weather-proofing material for the modifications to the family room roof. The existing skylights will be removed to make room for the sunroom roof attachment.
Friday, August 12, 2022
Subscribe to:
Post Comments (Atom)
Windows! We were surprised today with the delivery of the last four glass windows for the west wall. Unfortunately, three of the four windo...
-
Windows! We were surprised today with the delivery of the last four glass windows for the west wall. Unfortunately, three of the four windo...
-
The remaining tiles were installed today, and will be ready for grouting tomorrow. We look forward to being able to use the sunroom on Frida...
-
Day 26 - There were no installers yesterday, but the electrician worked today to finish the rough-in wiring in preparation for the inspectio...