Day 11 - After a 4" rain last night and another brief rainfall this morning, the sunroom had standing water on the floor boards and the roof was too wet to work on. At 9am a two-man crew arrived with a load of pressure-treated boards and posts and vinyl sleeve material for the deck bench frames. By the end of the work day, the bench frames were nearly completed, with a few blocking/support boards remaining to be installed. The bench frames will be covered with Trex boards when the deck flooring is installed.
Thursday, August 11, 2022
Subscribe to:
Post Comments (Atom)
Windows! We were surprised today with the delivery of the last four glass windows for the west wall. Unfortunately, three of the four windo...
-
Windows! We were surprised today with the delivery of the last four glass windows for the west wall. Unfortunately, three of the four windo...
-
The remaining tiles were installed today, and will be ready for grouting tomorrow. We look forward to being able to use the sunroom on Frida...
-
Day 26 - There were no installers yesterday, but the electrician worked today to finish the rough-in wiring in preparation for the inspectio...