Tuesday, August 2, 2022

Day 4 - The crew attached extensions to their post hole digging tools to complete excavating the 3 remaining footer holes to a depth of 8 feet.  Shortly afterwards, the county inspector arrived and approved the foundation holes.


All of the available concrete mix was poured and more will be needed to be at the desired height. Meanwhile, all of the framing material was staged in the backyard for assembly. 


Here's how the project looked at the end of the day.


And the highlight of the day was the delivery of the porta-potty. It certainly dresses up our front yard, and we know the neighbors will love it.







 

No comments:

Post a Comment

 Windows! We were surprised today with the delivery of the last four glass windows for the west wall. Unfortunately, three of the four windo...