Durock Day
The tile installers installed a Durock tile support system today. Here's the process:
- Wipe entire sub-floor with a damp sponge
- Secure the existing sub-floor with additional screws
- Apply mortar to the sub-floor
- Apply 1/4" thick 3 ft x 5 ft Durock cement boards
- Secure Durock with 1-1/2" screws
- Tape all seams
- Spread mortar on all seam tape
We walked on the Durock after the mortar had dried for a few hours, and it feels like you are walking on a sidewalk - VERY solid!
Tile installation is scheduled for tomorrow (Tuesday), and will take one to two days, followed by grouting.