Day 14 - A two-man crew installed the Trex cover boards for the top of the benches this morning. They moved on to the initial roof work, removing the Family Room skylights and covering the holes with wood panels and tar paper. They also installed part of the roof center beam for the sunroom.
Tuesday, August 16, 2022
Subscribe to:
Post Comments (Atom)
Windows! We were surprised today with the delivery of the last four glass windows for the west wall. Unfortunately, three of the four windo...
-
Landscaping Day 5 - The 4-man crew arrived at 9:45 with a truckload of mulch and more plants. They completed the pathways and retaining wall...
-
Landscaping day 4 - A large pile of topsoil was deposited on the street in front of our house early this morning. A four-man crew arrived at...
-
Day 26 - There were no installers yesterday, but the electrician worked today to finish the rough-in wiring in preparation for the inspectio...